Sl.No. | Name of the block/District | Area (In Sq Km) | Name of Mineral | ML Cum PL | Resource | Year of Auction |
---|---|---|---|---|---|---|
1 | Bhangaon/ West Singhbhum | 1.18 | Iron ore | ML | 39.00 MT | 2018 (28.06.2018) |
2 | Sons, Koiri Pathra/ Palamu | 96 Ha. | Graphite | ML | 0.67 MT | 2018 (03.08.2018) |
3 | Dulsulma | 36 | Graphite | ML | 1.72 MT | 2019 (01.03.2019) |
Sl. No. | Name of the block/District | Mineral | Area (in Hectares) |
Estimated Reserve (in MT)* |
Level of Exploration | ML/ PL Cum ML | Update Position of Auction |
---|---|---|---|---|---|---|---|
1 | Hariyan, Barunmuti, Thurkubera/ East Singhbhum |
Emerald | 83.1 | 51557.00 kg | G-3 | PL Cum ML | As per suggestion of Ministry of Mines, GoI, NMDC has been nominated for detail exploration in this area. |
2 | Bahutiya/ East Singhbhum |
Emerald | 05 | 9200.00 kg | G-3 | PL Cum ML | |
3 | Dudhapat/ Lohardaga | Bauxite | 130 | 9.05 MT | G-2 | ML | Bauxite rate is awaited from GoI. |
4 | Ponchi | Graphite | 10 | 0.36 MT | G-2 | ML | Area falls in Eco-Sensitive Zone |
5 | Khutiya* (Dhurki) | Dolomite/ Limestone | 100 | Limestone- 0.195 MT Dolomite- 1.53 MT |
G-2 | ML | Report submitted for auction in Oct 2018. |
6 | Piyartand/ Ranchi | Limestone | 112 | 0.54 MT | G-2 | ML |
Sl.No. | Mineral | Area | District | Level of Exploration | Status of work | Expected date of submission of GR and DGPS Survey Report |
---|---|---|---|---|---|---|
1 | Iron ore | Thakura 10 (a) 2 (c) Block |
West Singhbhum | G2 | Drilling work stopped. | Area falls under no mining zone. Hence not considered for auction after G-3 level of work. |
2 | Iron ore | Diriburu 10 (a) 2 (c) Block |
West Singhbhum | G2 | Drilling work stopped. | |
3 | Manganese | Dangdung | East Singhbhum | G4 | Mapping work competed. Report submitted. | Forest Department denied permission of drilling in this area as area falls under Eco Sensitive Zone. |
4 | Manganese | Paharpur | East Singhbhum | G4 | Mapping work competed. Report submitted. | |
5 | Manganese | Bawariya | West Singhbhum | G2 | Geological work stopped as area falls under no mining zone. |
Sl.No. | Name of the block/ District | Mineral | Area (in Hectares) |
Estimated Reserve (in MT)* |
Level of Exploration | ML/ PL Cum ML | Update Position of Auction | Expected date of submission of GR for auction |
---|---|---|---|---|---|---|---|---|
1 | Nandup (East), Bayanbil (Combined Block)
Geological Report of MECL |
Copper | 86 | 0.087 MT (0.5% Cu) 0.075 MT (0.2% Cu) in Nandup (East) 0.114 MT (0.2% Cu) in Bayanbil |
G-2 | ML | Ready for auction. | Report has submitted for auction on 15.01.2019. |
Sl. No. | Name of the block/District | Mineral | Area (in Sq Km) | Estimated Reserve (in MT)* | Level of Exploration | ML/ PL Cum ML | Update Position of Auction |
---|---|---|---|---|---|---|---|
1 | Dhuluapat Bauxite Block of Lohardaga District of Jharkhand (Geological Report of GSI) | Bauxite | 1.80 | 2.30 MT
(46.78 Al2O3) |
G-2 | ML | DGPS Survey report received. Form IV A is awaited from GSI. After receiving form IV A block will be available for auction. |
Sl. No. | Mineral | Area | District | Proposed Level of Exploration | Status of work | Expected date of submission of GR and DGPS Survey Report |
---|---|---|---|---|---|---|
1 | Limestone (Special Programme) |
Bhawnathpur | Palamu | G2 | M/s. SAIL has submitted three reports of the area Ghaghra, Goregaon and Saraiya of Bhawnathpur area. Earlier Directorate of Geology have prepared composite report of Saraiya and Goregaon area on the basis of data provided by M/s. SAIL. Boundary demarcation work of composite area has also been done by Directorate of Geology. | After surrender of lease, auction process can be initiated. |
Sl. No. | Mineral | Area | District | Proposed Level of Exploration | Status of work with expected date of completion | Expected date of submission of Block for Auction | ||||
---|---|---|---|---|---|---|---|---|---|---|
Mapping | Drilling | Analysis of samples | DGPS Survey Report | GR preparation | ||||||
1 | Bauxite | Lodhapat | Gumla | G-2 | Complete | Complete | Complete | Complete | Complete | April 2019 |
2 | Graphite | Rewaratu | Palamu | G3/G2 | Complete | In progress/May 2019 | July 2019 | Sept 2019 | Oct 2019 | October 2019 |
3 | Bauxite | Chiropat | Gumla | G2 | Complete | Complete | In progress/May 2019 | In progress/July 2019 | July 2019 | July 2019 |
4 | Graphite | Bhusariya Tola | Palamu | G2 | Geological work stopped as area falls under Eco Sensitive Zone. | |||||
5 | Graphite | Chanpi | Palamu | G2 | Complete | Proposal received/Aug 2019 | Oct 2019 | Nov 2019 | Nov 2019 | Nov 2019 |
Sl. No. | Mineral | Area | District | Proposed Level of Exploration | Status of work with expected date of completion | Expected date of submission of Block for Auction | ||||
---|---|---|---|---|---|---|---|---|---|---|
Mapping | Drilling | Analysis of samples | DGPS Survey Report | GR preparation | ||||||
1 | Manganese | Bhumru* | East Singhbhum | G2 | Complete/ Proposal for Geo-Physical Survey received | - | - | - | - | - |
2 | Manganese | Hatibari | East Singhbhum | G2 | In progress/ April 2019 | Sept 2019 | Nov 2019 | Nov 2019 | Nov 2019 | Dec 2019 |
3 | Bauxite | Paintoli | Gumla | G2 | Will start in May 2019 | Nov 2019 | Dec 2019 | Jan 2020 | Jan 2020 | Jan 2020 |
4 | Bauxite | Dhwajapat Toli | Gumla | G2 | Will start in June 2019 | Nov 2019 | Dec 2019 | Jan 2020 | Jan 2020 | Jan 2020 |
5 | Graphite | Sokra | Palamu | G2 | Will start in June 2019 | Dec 2019 | Jan 2020 | March 2020 | March 2020 | March 2020 |
6 | Dolomite/ Limestone | Hesaldag | Garhwa | G2 | MECL will carry out this project. |
In light of agreement signed between State Government and M/s. MECL total 20 proposals for geological exploration have been submitted to M/s. MECL. 10 proposals for G-2 level of exploration are received from M/s. MECL. Work order of geological exploration against 5 proposals was given to MECL. MECL has started exploration in 3 Mineral Blocks. Due to some local/technical issues work did not commence in two mineral blocks. Work Order for three mineral blocks has been given in January 2019. Out of three work started in one mineral block. Work order for rest two blocks will be given after Parliament Election.
Sl. No. | Name of Mineral Block/District | Proposed Area | Proposal Cost | Date of Commencement | Status of work |
---|---|---|---|---|---|
1 | Amtipani Bauxite Block/ Gumla | 253.00 Ha./1.136 Sq Km | 288.625 Lakh | January 2018 | First phase complete. Due to some local law and order problem work abandoned. |
2 | Harup Bauxite Block/ Gumla | 59.08 Ha./0.260 Sq Km | 89.033 Lakh | April 2018 | Final GR submitted |
3 | Ligirpat (Dokapat) Bauxite Block/ Gumla | 153.35 Ha./1.284 Sq Km | 287.805 Lakh | March 2018 | Due to some local law and order problem work abandoned. |
4 | Kujam Bauxite Block/ Gumla | 51.67 Ha./0.295 Sq Km | 112.481 Lakh | May 2018 | Work abandoned due to overlapping of area. |
5 | Serengdag (Salangi Village) Bauxite Block/ Gumla Mahuapattoli-Harduba Bauxite Block/ Gumla |
126.81 Ha./0.603 Sq Km | 196.757 Lakh | January 2018 | Geological report under preparation |
Sl. No. | Name of Mineral Block/District | Proposed Area | Time of completion as per proposal of MECL | Status |
---|---|---|---|---|
1 | Pulung Pat Bauxite Block/ Lohardaga | 1.58 Sq Km | 06 Months | Work order to be issued in 2019-20 |
2 | Garh Pat Bauxite Block/ Lohardaga | 1.55 Sq Km | 13 Months | Work order issued in the month of January 2019. Forest clearance for drilling required. |
3 | Khamar Pat Bauxite Block/ Lohardaga | 1.21 Sq Km | 08 Months | - |
4 | Madua Pat Bauxite Block/ Lohardaga | 1.225 Sq Km | 08 Months | Work started. |
5 | Madua Pat (N) Bauxite Block/ Lohardaga | 1.22 Sq Km | 08 Months |
Sl. No. | Lessee Name/Mauza | Area (Ha.) | Status of GR |
---|---|---|---|
1. | Smt. Devkabai Velji/ Ajitaburu | 46.62 | GR submission - April 2019 |
2. | M/s. Rungta Mines Pvt. Ltd./Meralgara, Barabaljori | 115.22 | GR submission - April 2019 |
3. | M/s. Rungta Mines Pvt. Ltd./ Ghatkuri | 138.845 | GR submission - April 2019 |
4. | M/s. Vijay Kumar Ojha/ Barabaljori | 21.246 | GR submission - April 2019 |
5. | M/s. Rajeshwar Jute Mills Ltd./ Baraiburu, Tatiba | 258.98968 | GR submission - April 2019 |
6. | NKPK/ Ghatkuri R.F. | 149.74 | GR submission - April 2019 |
SL. No. | Lessee Name | Lease Details | Estimated Reserves (in Million Tone) | Present level of exploration (G1 to G4: as per MEMCR, 2015) | Remarks | |
---|---|---|---|---|---|---|
Mauza | Area | |||||
1 | NKPK | Noamundi | 66.781 Ha. | - | - | Geological mapping complete. After getting permission from GoI drilling work will be start. |
2 | Shri Ram Mineral Company | Khas Jamda | 265.88 Ha. | Iron - 0.69 Manganese - 0.70 | Nos. of bore holes 15 random spacing. Reserve estimation on quarry exposure. | Geological mapping started. |
3 | Padam Kumar Jain | Thakurani | 84.68 Ha. | Iron - 33.03 | Nos. of bore holes 40 core drilling and 14 DTH. | Geological mapping complete. After getting permission from GoI drilling work will be start. |
4 | Revati Raman Ojha | Noamundi & Meralgara | 62.43 Ha. | - | - | Geological mapping started. |
SL. No. | Lessee Name | Lease Details | Estimated Reserves (in Million Tone) | Present level of exploration (G1 to G4: as per MEMCR, 2015) | Remarks | |
---|---|---|---|---|---|---|
Mauza | Area | |||||
1 | Shri M.L. Jain & Sons | Karampada R.F. | 202.35 Ha. | - | - | Geological exploration commenced from April 2019.(As reported by GSI) |
2 | M/s R. Mechdil | Karampada R.F. | 110.08 Ha. | - | - | |
3 | Sri Kamaljeet Singh Ahluwalia | Baraiburu | 129.499 Ha. | Iron - 1.50 Manganese - 2.60 | Reserve estimation on quarry exposures. | |
4 | Sri Kamaljeet Singh Ahluwalia | Baraiburu/Tatiba | 250.763 Ha. | Iron - 5.22 Manganese - 6.97 | Reserve estimation on quarry exposures. |
SL. No. | Lessee Name | Lease Details | Estimated Reserves (in Million Tone) | Present level of exploration (G1 to G4: as per MEMCR, 2015) | Remarks | |
---|---|---|---|---|---|---|
Mauza | Area | |||||
1 | Revati Raman Ojha | Itarbaljori | 37.737 Ha. | - | - | Non mining zone as per MPSM report |
2 | M/s Khatao Liladhar Thakkar | Kumirita | 30.84 Ha. | Iron - 0.515 | Only DTH bore hole but data not available. Reserve estimation on quarry exposures. | Non mining zone as per MPSM report |
3 | Sri Chandra Prakash Sharda | Itarbaljori | 57.466 Ha. | Iron - 0.539 | 20 DTH Bore holes in 8.85 Ha. Reserve estimation on the basis of this data. | Non mining zone as per MPSM report |
4 | M/s General Produce Company | Ghatkuri R.F. | 70.680 Ha. | - | - | 35.34 Ha is under no mining zone as per MPSM report. |
Total minor mineral blocks (Stone, Granite, Mica and Quartz) prepared and sent for auction– 44.
Most of the Geologists are engaged in Parliament Election therefore in the month of April 2019 progress of work affected.